Home
Download PDF
Order CD-ROM
Order in Print
Home
>
UFGS Criteria Document Report
>
> 02115A
SECTION 02115A UNDERGROUND STORAGE TANK REMOVAL
PART 1. GENERAL - 02115A0004
REFERENCES - 02115A0005
ASTM INTERNATIONAL (ASTM) - 02115A0006
SUBMITTALS - 02115A0007
QUALIFICATIONS - 02115A0008
REGULATORY REQUIREMENTS - 02115A0009
Sequencing and Scheduling - 02115A0010
BACKFILL MATERIAL
GENERAL REQUIREMENTS - 02115A0012
Analysis
CLEARING, GRUBBING AND REMOVALS
Contaminated Water Disposal
PURGING AND INERTING
EXCAVATION - 02115A0017
Stockpiles
REMOVAL OF PIPING, ANCILLARY EQUIPMENT, AND TANK
Contaminated Soil, Tank and Piping Excavation Examination
TANK CLEANING
SOIL EXAMINATION, TESTING, AND ANALYSIS
Stockpiled Material Sampling
BACKFILLING - 02115A0024
DISPOSAL REQUIREMENTS
Tank and Ancillary Equipment Disposal
Documentation of Treatment or Disposal
Tank Closure Reports shall include the following information as a minimum
Tank Closure Reports shall include the following information as a minimum (cont.)
02115A