Storage, and Disposal (TSD) facilities.
**************************************************************************
The work shall consist of removal, decontamination and disposal of [one]
[_____], [_____] L gallon underground storage tank and associated piping
and ancillary equipment. The [tank is] [tanks are] constructed of [steel]
[fiberglass] [_____] and [is] [are] at [the location shown on the drawings]
[the following location: [_____]]. The [_____] L gallon tank was used for
storing [leaded gasoline] [unleaded gasoline] [fuel oil] [diesel fuel]
[waste oil] [diesel oil] [hazardous waste] [_____] and was taken out of
service in [_____]. Residue remaining in the tank is considered a
[special] [hazardous] waste. Subsurface conditions are represented
[herein] [on drawings] [in Appendix [_____]] [_____]. Existing native
soils are predominantly [_____]. Available backfill material is typically
[_____]. Groundwater [has been encountered within [_____] m feet of the
surface] [is not expected to be encountered]. The Contractor shall verify
the actual conditions prior to submitting a bid. The site [shall be treated
as a hazardous waste site and] [is not a hazardous waste site but] shall be
given special consideration due to the nature of the materials and hazards
present until closure activities are complete.
1.6.1
Sequencing and Scheduling
**************************************************************************
NOTE: 40 CFR 280, RCRA Subtitle I closures are
primarily performed on petroleum or chemical product
tanks and require a minimum of 30 days notice prior
to a change in service or closure.
The RCRA Subtitle C tank closures fit into three
categories:
a. Hazardous waste accumulation tanks as per 40 CFR
262.34(a)(1)(ii). These tanks store hazardous waste
for less than 90 days.
b. Tanks storing hazardous waste over 90 days
without a permit (illegal storage).
c.
Part B permitted storage tanks.
The Installation Environmental Coordinator should
decide who is responsible for contacting the
Implementing Agency. Subtitle C tank closures
should be accomplished in accordance with the
closure plans previously prepared and approved, and
other applicable regulatory standards including the
Land Ban 40 CFR 268 requirements.
**************************************************************************
The Contractor shall notify the Installation Environmental Coordinator and
the Contracting Officer [_____] days prior to tank removal. The
[Contractor shall] [Contracting Officer will] [Installation Environmental
Coordinator will] be responsible for contacting the Implementation Agency
(IA) [_____] in accordance with the applicable reporting requirements.
1.6.2
Work Plan
The Contractor shall develop, implement, maintain, and supervise as part of
SECTION 02115A
Page 10