1.8.2
Government Approved
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
Government approval is required for extensions of design, critical
materials, deviations, equipment whose compatibility with the entire system
must be checked, and other items as designated by the Contracting Officer.
Government approval is required for any deviations from the Solicitation or
Accepted Proposal and other items as designated by the Contracting Officer.
Within the terms of the Contract Clause entitled "Specifications and
Drawings for Construction," they are considered to be "shop drawings."
1.8.3
Government Reviewed Design or Extension of Design
**************************************************************************
NOTE: This paragraph applies only to design-build
construction projects. The DESIGN AFTER AWARD
section is project specific and usually carries the
number 01012.
**************************************************************************
The Government will review all (_____%) and (_____%) design submittals for
conformance with the technical requirements of the solicitation. Section
[_____] DESIGN AFTER AWARD covers the design submittal and review process
in detail. Government review is required for extension of design
construction submittals, used to define contract conformity, and for
deviation from the completed design. Review will be only for conformance
with the contract requirements. Included are only those construction
submittals for which the Designer of Record design documents do not include
enough detail to ascertain contract compliance. The Government may, but is
not required, to review extensions of design such as structural steel or
reinforcement shop drawings.
1.8.4
Information Only
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
All submittals not requiring Government approval will be for information
only.All submittals not requiring Designer of Record or Government approval
will be for information only. They are not considered to be "shop
drawings" within the terms of the Contract Clause referred to above.
All submittals not requiring Government approval will be for information
only. They are not considered to be "shop drawings" within the terms of
the Contract Clause referred to above.
1.9
APPROVED SUBMITTALS
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
The Contracting Officer's approval of submittals shall not be construed as
SECTION 01330
Page 21