1.16.2
Deviations
For submittals which include proposed deviations requested by the
Contractor, the column "variation" of ENG Form 4025 shall be checked. The
Contractor shall set forth in writing the reason for any deviations and
annotate such deviations on the submittal. The Government reserves the
right to rescind inadvertent approval of submittals containing unnoted
deviations.
1.17
CONTROL OF SUBMITTALS
The Contractor shall carefully control his procurement operations to ensure
that each individual submittal is made on or before the Contractor
scheduled submittal date shown on the approved "Submittal Register."
1.18
GOVERNMENT APPROVED SUBMITTALS
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
Upon completion of review of submittals requiring Government approval, the
submittals will be identified as having received approval by being so
stamped and dated. [_____] copies of the submittal will be retained by the
Contracting Officer and [_____] copies of the submittal will be returned to
the Contractor. If the Government performs a conformance review of other
Designer of Record approved submittals, the submittals will be so
identified and returned, as described above.
1.19
INFORMATION ONLY SUBMITTALS
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
Normally submittals for information only will not be returned. Approval of
the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any
item found not to comply with the contract. This does not relieve the
Contractor from the obligation to furnish material conforming to the plans
and specifications; will not prevent the Contracting Officer from requiring
removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples
for testing by the Government laboratory or for check testing by the
Government in those instances where the technical specifications so
prescribe. For design-build construction the Government will retain
[_____] copies of information only submittals.
1.20
STAMPS
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
Stamps used by the Contractor on the submittal data to certify that the
submittal meets contract requirements shall be similar to the following:
SECTION 01330
Page 26