specification, including shop drawings, product data and samples. One copy
of the transmittal form for all submittals shall be forwarded to the
Resident Officer in Charge of Construction.
[The Architect-Engineer for this project] [NAVFAC Atlantic] will review and
approve for the Contracting Officer those submittals reserved for
Contracting Officer approval to verify submittals comply with the contract
requirements.
1.7.1.1
O&M Data
[The Architect-Engineer for this project] [NAVFAC Atlantic] will review and
approve for the Contracting Officer O&M Data to verify the submittals
comply with the contract requirements.; submit data specified for a given
item within 30 calendar days after the item is delivered to the contract
site.
a.
In the event the Contractor fails to deliver O&M Data within the
time limits specified, the Contracting Officer may withhold from
progress payments 50 percent of the price of the item with which
such O&M Data are applicable.
[1.7.1.2
Submittals Reserved for NAVFAC Atlantic Approval
**************************************************************************
NOTE: Include this optional paragraph for all
projects designed by Architect-Engineer consulting
firms. Fill in the appropriate specification
section numbers and titles for the respective
products.
**************************************************************************
As an exception to the standard submittal procedure specified above, submit
the following to the Commander, NAVFAC Atlantic, Code CI4A1, 6506 Hampton
Blvd, Norfolk, VA 23508-1278:
**************************************************************************
NOTE: Add Section Reference tags where appropriate
below when blanks are filled.
**************************************************************************
[a.
Section [_____], "[_____]": Pile driving records]
[b.
Section [_____], "[_____]": All fire protection system submittals]
[c.
Section [_____], "[_____]": All fire alarm system submittals]
[d.
Section 15901N SPACE TEMPERATURE CCONTROL SYSTEMS: SD-06 field
test report submittals]
[e.
Section 15910N DIRECT DIGITAL CONTROL SYSTEMS: SD-06 field test
report submittals]
[f.
Section 15950N HVAC TESTING/ADJUSTING/BALANCING: All submittals]
[g.
Section 15951N TESTING INDUSTRIAL VENTILATION SYSTEMS: All
submittals]
[h.
SECTION 01330
Page 19