submittals]
[i.
submittals]
[j.
Section 16301N OVERHEAD TRANSMISSION AND DISTRIBUTION:
[k.
Section 16360 SECONDARY UNIT SUBSTATIONS: Transformer submittals]
[l.
Section 16361N PRIMARY UNIT SUBSTATIONS: Transformer submittals]
][1.7.1.3
Overseas Shop Drawing Submittals
**************************************************************************
NOTE: For use on overseas jobs only.
**************************************************************************
All submittals shall be sent via overnight express mail service. All costs
associated with the overnight express mail service shall be borne by the
construction Contractor. Costs associated with the overnight express mail
of submittals related to proposed submittal variances of resubmittals
necessary as a result of noncompliant or incomplete Contractor submittals
shall be the responsibility of the Contractor.
]
1.8
SUBMITTAL CLASSIFICATION
**************************************************************************
NOTE: The remaining paragraphs of this
specification section are for Army projects only.
**************************************************************************
Submittals are classified as follows:
1.8.1
Designer of Record Approved
**************************************************************************
NOTE: This paragraph applies only to design-build
projects. The DESIGN AFTER AWARD section is project
specific and usually carries the number 01012.
**************************************************************************
Designer of Record approval is required for extensions of design, critical
materials, any deviations from the solicitation, the accepted proposal, or
the completed design, equipment whose compatibility with the entire system
must be checked, and other items as designated by the Contracting Officer.
Within the terms of the Contract Clause entitled "Specifications and
Drawings for Construction", they are considered to be "shop drawings". The
Contractor shall provide the Government the number of copies designated
hereinafter of all Designer of Record approved submittals. The Government
may review any or all Designer of Record approved submittals for
conformance to the Solicitation and Accepted Proposal. The Government will
review all submittals designated as deviating from the Solicitation or
Accepted Proposal, as described below. Design submittals shall be in
accordance with Section [_____] DESIGN AFTER AWARD. Generally, design
submittals should be identified as SD-05 DESIGN DATA submittals.
SECTION 01330
Page 20