a complete check, but will indicate only that the general method of
construction, materials, detailing and other information are satisfactory
design, general method of construction, materials, detailing and other
information appear to meet the Solicitation and Accepted Proposal.
Approval will not relieve the Contractor of the responsibility for any
error which may exist, as the Contractor under the Contractor Quality
Control (CQC) requirements of this contract is responsible for [dimensions,
the design of adequate connections and details, and the satisfactory
construction of all work][design, dimensions, all design extensions, such
as the design of adequate connections and details, etc., and the
satisfactory construction of all work]. After submittals have been
approved by the Contracting Officer, no resubmittal for the purpose of
substituting materials or equipment will be considered unless accompanied
by an explanation of why a substitution is necessary.
1.10
DISAPPROVED SUBMITTALS
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
The Contractor shall make all corrections required by the Contracting
Officer and promptly furnish a corrected submittal in the form and number
of copies specified for the initial submittal.The Contractor shall make all
corrections required by the Contracting Officer, obtain the Designer of
Record's approval when applicable, and promptly furnish a corrected
submittal in the form and number of copies specified for the initial
submittal. Any "information only" submittal found to contain errors or
unapproved deviations from the Solicitation or Accepted Proposal shall be
resubmitted as one requiring "approval" action, requiring both Designer of
Record and Government approval. If the Contractor considers any correction
indicated on the submittals to constitute a change to the contract, a
notice in accordance with the Contract Clause "Changes" shall be given
promptly to the Contracting Officer.
1.11
WITHHOLDING OF PAYMENT
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
Payment for materials incorporated in the work will not be made if required
approvals have not been obtained.No payment for materials incorporated in
the work will be made if all required Designer of Record or required
Government approvals have not been obtained. No payment will be
made for any materials incorporated into the work for any conformance
review submittals or information only submittals found to contain errors or
deviations from the Solicitation or Accepted Proposal.
1.12
GENERAL
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
The Contractor shall make submittals as required by the specifications.
SECTION 01330
Page 22