for use by approving authority. Direct specific attention in
writing or on resubmitted submittal, to revisions not requested by
approving authority on previous submissions.
e.
Furnish additional copies of submittal when requested by
Contracting Officer, to a limit of 20 copies per submittal.
f.
Complete work which must be accomplished as basis of a submittal
in time to allow submittal to occur as scheduled.
g.
Ensure no work has begun until submittals for that work have been
returned as "approved," or "approved as noted", except to the
extent that a portion of work must be accomplished as basis of
submittal.
1.4.6
QC Organization Responsibilities
a.
Note date on which submittal was received from Contractor on each
submittal.
b.
Review each submittal; and check and coordinate each submittal
with requirements of work and contract documents.
c.
Review submittals for conformance with project design concepts and
compliance with contract documents.
d.
Act on submittals, determining appropriate action based on QC
organization's review of submittal.
(1) When QC manager is approving authority, take appropriate
action on submittal from the possible actions defined in paragraph
entitled, "Actions Possible."
(2) When Contracting Officer is approving authority or when
variation has been proposed, forward submittal to Government with
certifying statement or return submittal marked "not reviewed" or
"revise and resubmit" as appropriate. The QC organization's
review of submittal determines appropriate action.
e.
Ensure that material is clearly legible.
f.
Stamp each sheet of each submittal with QC certifying statement or
approving statement, except that data submitted in bound volume or
on one sheet printed on two sides may be stamped on the front of
the first sheet only.
(1) When approving authority is Contracting Officer, QC
organization will certify submittals forwarded to Contracting
Officer with the following certifying statement:
"I hereby certify that the (equipment) (material) (article) shown and
marked in this submittal is that proposed to be incorporated with
contract Number [_____], is in compliance with the contract
drawings and specification, can be installed in the allocated
spaces, and is submitted for Government approval.
Certified by Submittal Reviewer _____________________, Date _______
(Signature when applicable)
SECTION 01330
Page 12