designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as
otherwise designated. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government. The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Submittal register; G
1.3
USE OF SUBMITTAL REGISTER [DATABASE]
**************************************************************************
NOTE: The following paragraphs, up to the paragraph
entitled "SUBMITTAL CLASSIFICATION", are for Navy
projects only.
**************************************************************************
**************************************************************************
NOTE: Create the submittal register from the
project specification files, at the conclusion of
the design. In SGML SPECSINTACT, choose "Submittal
Register Program" from "Forms/Documents" pull-down
menu. Local procedures must be responsive to the
requirement that the submittal register, required
with the QA plan, is usually due from the Contractor
within 20 days after the Notice of Award.
**************************************************************************
**************************************************************************
NOTE: Include the bracketed text, invoking the use
of the electronic database for submittals, in most
projects. The alternative is a manually processed
submittal register initially created from the
Submittal Register Program, which may be appropriate
for small projects.
**************************************************************************
Submittal register [database and submittal management program] will be
delivered to the Contractor, by Contracting Officer [on 3 1/2 inch disk].
Register[ database] will have the following fields completed, to the extent
SECTION 01330
Page 7