1.3.2
Contractor Use of Submittal Register
Update the following fields[ in the Government-furnished submittal register
program or equivalent fields in program utilized by Contractor].
Column (b) Transmittal Number:
Contractor assigned list of
Column (j) Action Code (k): Date of action used to record
Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.3.3
Approving Authority Use of Submittal Register
Update the following fields[ in the Government-furnished submittal register
program or equivalent fields in program utilized by Contractor].
Column (b).
Column (l) List date of submittal receipt.
Column (m) through (p).
Column (q) List date returned to Contractor.
1.3.4
Contractor Action Code and Action Code
Entries used shall be as follows (others may be prescribed by Transmittal
Form):
NR - Not Received
AN - Approved as noted
A - Approved
RR - Disapproved, Revise, and Resubmit
1.3.5
Copies Delivered to the Government
**************************************************************************
NOTE: Include the bracketed text, invoking the use
of the electronic database for submittals, in most
projects. The alternative is a manually processed
submittal register initially created from the
Submittal Register Program, which may be appropriate
for small projects.
**************************************************************************
Deliver one copy of submittal register updated by Contractor to Government
with each invoice request. [Deliver in electronic format, unless a paper
copy is requested by Contracting Officer.]