with no relationship lines displayed in the graphic. ][Include [1
copy][____ copies] of the Design Network Analysis Schedule on electronic
media that is acceptable to the Contracting Officer.]]
1.7.3
Construction Network Analysis Schedule
**************************************************************************
NOTE: Include the first set of brackets if the
project is Design Build, the second set of brackets
will be used for Design-Bid-Build. When
Fast-Tracking is required or an option for the
project, include the third set of brackets.
**************************************************************************
**************************************************************************
NOTE: When WebCM is a requirement on this project,
use the fourth set of bracketed sentences and delete
the fifth bracketed sentence of this paragraph.
**************************************************************************
[If design must be completed and accepted prior to construction,
submit][Submit] the complete network analysis schedule and obtain
acceptance prior to starting construction work.[ If the project will be
Fast-Tracked, each construction stage will be built upon the previous
Fast-Tracked Baseline Schedule (including any interim updates thereto) and
accepted prior to starting that stage of the construction work.][ So as to
capture performance to date, this schedule shall be built upon as an
extension of the most current accepted update of the Design schedule.]
Submit [three][____] copies of the diagrams described in the paragraph
entitled "Diagrams" and the reports listed in the paragraph entitled
"Required Tabular Reports". As part of this submittal, provide the Project
Name format (and Project Group Name if used) that will be used by the
Contractor to identify initial schedule submittals, updates, fragnets,
changes, etc. [Backed-up native files (.prx or .stx) for the schedule
submittal will be posted to the NAVFAC WebCM internet site, as directed by
the Contracting Officer. The project schedule will also be posted in the
format specified as an Adobe PDF file with no relationship lines displayed
in the graphic. ][Include [1 copy][_____ copies] of the Construction
Contracting Officer.]
1.7.4
Review and Evaluation
After the Government's review(s) of the [Design Network Analysis Schedule
and ]Construction Network Analysis Schedule, the Contractor shall meet with
the Contracting Officer to discuss the review and evaluation of the NAS
submittal. Revisions necessary as a result of this review shall be
resubmitted for acceptance within 10 calendar days after the meeting.
1.7.5
Baseline Network Analysis Schedule
Once review comments are resolved and the Contracting Officer has accepted
the [Design Network Analysis Schedule and ]Construction Network Analysis
Schedule, the Contractor shall within 5 calendar days furnish:
a.
[Two][_____] copies of the network diagrams.
b.
[Two][_____] copies of the reports listed in paragraph entitled
"Required Tabular Reports".