1.3.8
Capacity Calculations for Batteries
Calculation shall verify that the engine starting battery capacity exceeds
[1.3.9
Turbocharger Load Calculations
**************************************************************************
NOTE: When the engine-generator set installation
includes field installed exhaust system (i.e., the
engine-generator set is installed internal to a
building in lieu of in a self contained outdoor
enclosure), include the following paragraph.
**************************************************************************
When the proposed exhaust system layout is different from that shown on the
contract drawings, submit calculations showing that the external loads from
the exhaust system such as weight and thermal expansion do not exceed the
engine manufacturer's maximum allowed forces and moments on the
turbocharger.
]1.4
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************