This section applies to certain sections of[ Division 2, "Site
Construction,"][ Division 11, "Equipment,"][ Division 13, "Special
Construction,"][ and][ Division 14, "Conveying Systems"][ and][ Division
15, "Mechanical"]. This section applies to all sections of Division 16,
"Electrical," of this project specification unless specified otherwise in
the individual sections. This section has been incorporated into, and
thus, does not apply to, and is not referenced in the following sections.
Section
16272
Section
16273
Section
16360
SECONDARY UNIT SUBSTATIONS
Section
16402
ELECTRICAL DISTRIBUTION SYSTEM
Section
16442
SWITCHBOARDS AND SWITCHGEAR
Section
16510
INTERIOR LIGHTING
Section
16520
EXTERIOR LIGHTING
Section
16710
BUILDING TELECOMMUNICATIONS CABLING SYSTEM
Section
16711
TELECOMMUNICATIONS OUTSIDE PLANT
1.3
DEFINITIONS
a.
Unless otherwise specified or indicated, electrical and
electronics terms used in these specifications, and on the
drawings, shall be as defined in IEEE Std 100.
b.
The technical sections referred to herein are those specification
sections that describe products, installation procedures, and
equipment operations and that refer to this section for detailed
description of submittal types.
c.
The technical paragraphs referred to herein are those paragraphs
in PART 2 - PRODUCTS and PART 3 - EXECUTION of the technical
sections that describe products, systems, installation procedures,
equipment, and test methods.
1.4
ELECTRICAL CHARACTERISTICS
**************************************************************************
NOTE: Delete this paragraph for SOUTHNAVFACENGCOM
projects. Use IEEE C57.12.00 designations, such as
4160 V and 480Y/277 V, when referring to the primary
and secondary voltages, respectively, in the
following paragraph.
**************************************************************************
Electrical characteristics for this project shall be [_____] kV primary,
[single] [three] phase, [two] [three] [four] wire, [60] [50] [_____] Hz,
and [_____] volts secondary, [single] [three] phase, [three] [four] wire.
[substation] [manhole] [_____] shall be made by the [Contractor as directed
by the Contracting Officer] [Government].
1.5
ADDITIONAL SUBMITTALS INFORMATION
Submittals required in other sections that refer to this section must
conform to the following additional requirements as applicable.
SECTION 16050N