1.3.2.8
Reproducible Drawings
Submit one reproducible mylar shop drawing of each approved drawing sheet
to the Contracting Officer for the following items:
a.
Boiler layout, construction and details
b.
Breeching layout and details
c.
Burner control schematics and burner details
d.
e.
Fuel oil tanks, foundations and appurtenances
f.
Automatic feedwater recirculation system
g.
Piping schematics
1.3.3
Design Data
1.3.3.1
Engineering Calculations
Furnish the following calculations from the manufacturer:
a.
Foundation (including bearing and moment forces) and anchor bolts.
b.
Stack
(1) Stresses due to various loading conditions including wind and
seismic loads.
(2)
Vibration and damping.
(3)
Heat transfer at various design and ambient conditions.
(4)
Expansion profiles.
(5)
Shipping and erection stress analysis.
1.3.4
Test Reports
Submit the predicted economizer performance along with and as part
of the boiler predicted performance report.
1.3.5
Performance Requirements
1.3.5.1
Boiler
**************************************************************************
NOTE: When analyses of the specific fuels to be
burned are known, insert the proper values in this
paragraph. When unknown and the analyses given in FS
F-B-2902 are sufficient, omit this paragraph.
**************************************************************************
Base performance requirements, including furnace heat release rates, on the
following ultimate analysis and high heating values.