1.3.5.2
Economizer
The increase in efficiency due to the economizer shall be not less than
[_____] percent at full load. Fully coordinate the economizer with the
boiler to which it is to be applied.
1.3.5.3
Oil Burner/Windbox Package
Burner turndown ratio on specified fuel oil shall be not less than eight to
one, with excess air not over 15 percent at full steam load, and excess air
not over 22 percent at 20 percent steam load. [Air flow shall be modulated
through a single set of register louvers.]
1.3.5.4
Oil and Gas Burner/Windbox Package
Burner turndown ratio shall not be less than eight to one, when firing fuel
oil only and ten to one when firing natural gas only with excess air not
over 15 percent at full steam load, and excess air not over 22 percent at
20 percent steam load. [Air flow shall be modulated through a single set
of register louvers.]
1.4
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
SECTION 15511N
Page 23