1.3.2
System Calculations
Submit calculations showing that open-area smoke detectors calculations
comply with specified power consumption limitation requirements.
1.3.3
As-Built Drawings of Each System
After completion, but before final acceptance of the work, submit a
complete set of as-built working drawings of each system for record
purposes. Submit A1 841 x 594 mm 24 by 36 inches reproducible mylar film
with title block similar to full-size contract drawings. Furnish the
as-built (record) working drawings in addition to the as-built contract
drawings required by Division 1, "General Requirements."
1.4
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
[ The [_____] Division, Naval Facilities Engineering Command, Fire Protection
SECTION 13961N
Page 6