undamaged lengths of conduit according to size and type. Classify
supports, knobs, tubes, cleats, and straps as debris to be removed and
disposed.
3.1.18
Remove elevators, hoists, and similar conveying equipment and salvage as
whole units, to the most practical extent. Remove and prepare items for
salvage without damage to any of the various parts. Salvage and store
rails for structural steel with the equipment as an integral part of the
unit.
3.2
CONCURRENT EARTH-MOVING OPERATIONS
**************************************************************************
NOTE: Caution must be taken to prevent uncovered
holes and other such hazards. If work is to be
under a separate contract and subsequent filling is
not required under the separate contract,
arrangements must be made to have the filling done
under this contract.
**************************************************************************
Do not begin excavation, filling, and other earth-moving operations that
are sequential to demolition work in areas occupied by structures to be
demolished until all demolition in the area has been completed and debris
removed. Holes, open basements and other hazardous openings shall be
filled.
3.3
DISPOSITION OF MATERIAL
**************************************************************************
NOTE: This article entitled "Disposition of
Material" and the paragraphs that follow are for all
projects except as noted.
**************************************************************************
3.3.1
Title to Materials
**************************************************************************
NOTE: To minimize the possibility of contested
ownership of materials or equipment in structures to
be demolished, the following letter should be sent
to the station sufficiently in advance of the date
on which action is required, and the response
thereto incorporated in either the project
specifications or bidding documents. The Government
shall prepare this letter. For project prepared by
an A/E, the A/E shall notify the Government the need
for this correspondence.
From:
(Appropriate EDF Activity)
To:
Commanding Officer, (Station)
Subj:
Contract (Number) - [_____]:
(Including Demolition of [(_____)]
1.
This activity is preparing the documents
SECTION 02220
Page 18