hazardous waste, lead paint).
[1.6.7
Erosion and Sediment Control Inspection Reports
**************************************************************************
NOTE: Include this paragraph when construction
activities for clearing, grading, and excavation
result in the disturbance of 2 or more hectares 5 or
more acres of total land area (or a lesser amount of
total land area if applicable to comply with a
particular "State" requirements (e.g., required in
South Carolina in certain situations regardless of
the size of the land area disturbed)).
**************************************************************************
Submit "Erosion and Sediment Control Inspection Reports" (form provided at
the pre-construction conference) to the Contracting Officer once every 7
calendar days and within 24 hours of a storm event that produces 12 mm 0.5
inch or more of rain.
]1.6.8
Solid Waste Disposal Report
Monthly the Contractor will submit a solid waste disposal report to the
Contracting Officer. For each waste, the report will state the
classification (using the definitions provided in this section), amount,
location, and name of the business receiving the solid waste. The
Contractor will include copies of the waste handling facilities' weight
tickets, receipts, bills of sale, and other sales documentation. In lieu
of sales documentation, the Contractor may submit a statement indicating
the disposal location for the solid waste which is signed by an officer of
the Contractor firm authorized to legally obligate or bind the firm. The
sales documentation or Contractor certification will include the receiver's
tax identification number and business, EPA or State registration number,
along with the receiver's delivery and business addresses and telephone
numbers. For each solid waste retained by the Contractor for his own use,
the Contractor will submit on the solid waste disposal report the
information previously described in this paragraph. Prices paid or
received will not be reported to the Contracting Officer unless required by
other provisions or specifications of this Contract or public law.
1.7
WHM/HW MATERIALS PROHIBITION
**************************************************************************
NOTE: Use bracketed information in last sentence for
projects at Norfolk Naval Shipyard.
**************************************************************************
No waste hazardous material or hazardous waste shall be disposed of on
performance of this contract. The government is not responsible for
disposal of Contractor's waste material brought on the job site and not
required in the performance of this contract. The intent of this provision
is to dispose of that waste identified as waste hazardous
material/hazardous waste as defined herein that was generated as part of
this contract and existed within the boundary of the Contract limits and
not brought in from offsite by the Contractor. Incidental materials used
to support the contract including, but not limited to aerosol cans, waste
SECTION 01575N
Page 12