Accumulation areas; ensure only authorized personnel add wastes to
containers; ensure all Contractor personnel are trained in 40 CFR
requirements in accordance with their position requirements; coordinate
removal of waste containers; and maintain the Environmental Records binder
and required documentation, including environmental permits compliance and
close-out.
]1.12
ENVIRONMENTAL PROTECTION PLAN
Prior to inititating any work on site, the Contractor will meet with the
and develop a mutual understanding relative to the details of environmental
protection, including measures for protecting natural resources, required
will be submitted in the following format and will, at a minimum, address
the following elements (also refer to paragraph entitled "Protection of
Natural Resources" in this section):
a.
Description of the Environmental Protection Plan
(1)
General overview and purpose
(2)
General site information
**************************************************************************
NOTE: Include the following paragraph only if
paragraph entitled "Environmental Manager," is
included.
**************************************************************************
[(3) A letter signed by an officer of the firm appointing the
Environmental Manager and stating that he/she is responsible for
managing and implementing the Environmental Program as described
in this contract. Include in this letter the Environmental
Manager's authority to direct the removal and replacement of
non-conforming work.]
b.
Protection of Natural Resources
(1)
Land resources
(2)
Tree protection
(3)
Replacement of damaged landscape features
(4)
Temporary construction
(5)
(6)
Fish and wildlife resources
(7)
Wetland areas
c.
Protection of Historical and Archaeological Resources
(1)
Objectives
(2)
Methods
SECTION 01575N
Page 16