Notifications in the event of a release to the environment
f.
Protection of the Environment from Waste Derived from Contractor
Operations
(1)
Control and disposal of solid and sanitary waste
(2) Control and disposal of hazardous waste (Hazardous Waste
Management Section)
This item will consist of the management procedures for all
hazardous waste to be generated. The elements of those procedures
will coincide with the Activity Hazardous Waste Management Plan.
A copy of the Activity Hazardous Waste Management Plan will be
provided by the Contracting Officer. As a minimum, include the
following:
(a) Procedures to be employed to ensure a written waste
determination is made for appropriate wastes which are to be
generated;
(b)
Sampling/analysis plan;
(c) Methods of hazardous waste accumulation/storage (i.e., in
tanks and/or containers);
(d) Management procedures for storage, labeling, transportation,
and disposal of waste (treatment of waste is not allowed unless
specifically noted);
(e) Management procedures and regulatory documentation ensuring
disposal of hazardous waste complies with Land Disposal
Restrictions (40 CFR 268);
as lead-acid batteries, used oil, and the like;
(g)
Used oil management procedures in accordance with 40 CFR 279;
(h)
Pollution prevention\hazardous waste minimization procedures;
(i) Plans for the disposal of hazardous waste by permitted
facilities;
(j) Procedures to be employed to ensure all required employee
training records are maintained.
1.12.1
Environmental Protection Plan Review
approval. Commencement of work will not begin until the environmental
protection plan has been approved.
1.13
CONTRACTOR HAZARDOUS MATERIAL INVENTORY LOG
Submit the "Contractor Hazardous Material Inventory Log"(found at: