approval. After receipt by the Contractor of written approval of the
factory test/predelivery test procedures, the Contractor may schedule the
factory test/predelivery test.
1.3.4
Group IV Technical Data Package
1.3.4.1
Performance Verification Testing and Endurance Testing Data
**************************************************************************
NOTE: Insert section number and title for the
appropriate specifications.
**************************************************************************
The Contractor shall prepare a test plan and test procedures in accordance
with Section [_____] for the performance verification test and endurance
test. The test plan shall describe the applicable tests to be performed,
and other pertinent information such as specialized test equipment
required, and length of performance verification test. The test procedures
shall explain in detail, step-by-step actions and expected results to
demonstrate compliance with the requirements of this specification. The
Contractor shall deliver test plans for the performance verification test
and endurance test to the Government. After receipt by the Contractor of
written approval of the test plans, the Contractor shall deliver the
performance verification test and endurance test procedures for approval.
Written approval by the Government of the performance verification test
procedures shall be one of the prerequisites for commencing the performance
verification test as specified.
1.3.4.2
Operation and Maintenance Data
A draft copy of the operation and maintenance data, shall be delivered to
the Government prior to beginning the performance verification test for use
during site testing.
1.3.4.3
Training Data
Lesson plans and training data in manual format for the training phases,
including type of training to be provided, with a list of reference
material, shall be delivered for approval.
1.3.5
Group V Technical Data Package
1.3.5.1
Manuals
**************************************************************************
NOTE: Unless the installation has a specific
requirement, specify two copies of all manuals;
except for the Operator's Manual, which should be
specified to be six copies.
**************************************************************************
Final copies of the manuals bound in hardback, loose-leaf binders, shall be
delivered to the Government within 30 days after completing the endurance
test. The draft copy used during site testing shall be updated with any
changes required prior to final delivery of the manuals. Each manual's
contents shall be identified on the cover. The manuals shall include the
names, addresses, and telephone numbers of each subcontractor installing
equipment and systems, and of the nearest service representative for each
item of equipment and each system. The manuals shall have a table of