1.3.1.2
Manufacturers' Data
The data package shall include manufacturers' data for all materials
including field and system equipment provided under this specification.
1.3.1.3
DTS Description and Analyses
The data package shall include complete system descriptions, analyses, and
calculations used in selecting equipment required by these specifications.
Descriptions and calculations shall show how the equipment will operate as
a system to meet the performance of this specification. The data package
shall include the following:
a. MODEM or line driver receive and transmit levels, signal-to-noise
ratio calculations and assumed losses in decibels (dB) on each
communication circuit. Contractor shall use manufacturer's minimum and
maximum signal-to-noise ratio (db) of the actual equipment being
furnished for the DTS.
b. Communication speed and protocol description.
c. Data transmission system expansion capability and method of
implementation.
1.3.1.4
Certifications
All specified manufacturer's certifications shall be included with the data
package.
1.3.2
Group II Technical Data Package
The Contractor shall verify that site conditions are in agreement with the
design package. The Contractor shall submit a report to the Government
documenting changes to the site, or conditions that affect performance of
the system to be installed. For those changes or conditions which affect
system installation or performance, provide (with the report) specification
sheets, or written functional requirements to support the findings, and a
cost estimate to correct the situation. The Contractor shall not perform
any corrections without written permission from the Government.
1.3.3
Group III Technical Data Package
**************************************************************************
NOTE: Insert section number and title for the
specification.
**************************************************************************
The Contractor shall prepare a test plan and test procedures in accordance
with Section [_____] for the factory test. The test plan shall describe
the applicable tests to be performed, and other pertinent information such
as specialized test equipment required, length of factory test, and
location of the factory test/predelivery test. The procedures shall
explain in detail, step-by-step, actions and expected results to
demonstrate compliance with the requirements of this specification, and the
methods for simulating the necessary conditions of operation to demonstrate
performance of the system. The Contractor shall deliver the test plan for
the factory test/predelivery test to the Government. After receipt by the
Contractor of written approval of the test plan, the Contractor shall
deliver the factory test/predelivery test procedures to the Government for
SECTION 16792A
Page 8