SYSTEM; Section 13801A UTILITY MONITORING AND
CONTROL SYSTEMS (UMCS); Section 16751A CLOSED
CIRCUIT TELEVISION SYSTEMS.
**************************************************************************
1.4.2
Group II Technical Data Package
**************************************************************************
NOTE: If the designer has specified site condition
investigation in other sections, the first bracketed
sentence, with the proper section number inserted,
may be substituted in lieu of the second set of
bracketed sentences.
**************************************************************************
[The Group II technical data package is specified in Section [_____].] [The
Contractor shall verify that site conditions are in agreement with the
design package. The Contractor shall submit a report to the Government
documenting changes to the site, or differing conditions that affect
performance of the system to be installed. For those changes or conditions
which affect system installation or performance, specification sheets shall
be provided (with the report), or written functional requirements to
support the findings, and a cost estimate to correct the deficiency shall
be provided with the report. The Contractor shall not correct any
deficiency without written permission from the Government.]
1.4.3
Group III Technical Data Package
**************************************************************************
NOTE: Insert section number and title for the UMCS,
IDS, ESS or CCTV specifications.
**************************************************************************
The Contractor shall prepare test procedures and reports for the factory
test. A test plan and test procedures shall be prepared in accordance with
Section [_____] and this specification. The test procedures shall describe
the applicable tests to be performed, and other pertinent information such
as specialized test equipment required, length of test, and location of the
test. The procedures shall explain in detail, step-by-step actions and
expected results to demonstrate compliance with the requirements of this
specification, and the methods for simulating the necessary conditions of
operation to demonstrate performance of the system. The test report shall
describe the results of testing to include the date, time, location and
system component designations of material and equipment tested. Testing
action shall be recorded whether successful or not. Reasons for
termination of testing shall be described. Testing work sheets, printouts,
strip charts, oscilloscope or optical time domain reflectometer (OTDR)
printouts/photographs, raw and analyzed data, and testing conclusions shall
be included in the report. The Contractor shall deliver the factory test
procedures to the Government for approval. After receipt by the Contractor
of written approval of the test procedures, the Contractor may schedule the
factory test. The Contractor shall provide written notice of the test to
the Government at least 2 weeks prior to the scheduled start. The final
test report shall be delivered within 15 days after completion of the test.