should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
**************************************************************************
NOTE: Include the bracketed options on "CI44 and
074 review" for LANTNAVFACENGCOM and
SOUTHNAVFACENGCOM projects respectively. For other
projects, submittal review shall be performed by the
designer of record. If submittal review by
LANTNAVFACENGCOM or SOUTHNAVFACENGCOM is
specifically desired, the responsible Government
agency must coordinate with the respective Code CI44
or 074 during the design process. Add appropriate
information in Section 01330, "Submittal Procedures"
to coordinate with the special requirements.
**************************************************************************
[Submit in accordance with paragraph entitled "Coordinated Submittal
Reviews" herein].
1.3.1
Coordinated Submittal Reviews
a.
Submit transformer submittals to Code [CI44, Atlantic][074, Southern]
Division, Naval Facilities Engineering Command for approval. In
addition, submit one set of the remaining substation components for
SECTION 16361N
Page 9