[1.4.4
**************************************************************************
NOTE: Include bracketed option for separate
SOUTHNAVFACENGCOM projects only.
**************************************************************************
Drawings shall include, but are not limited to the following:
a.
An outline drawing, with top, front, and side views
b.
ANSI nameplate data
][1.4.5
Calibration Schedule
**************************************************************************
request for settings" for SOUTHNAVFACENGCOM projects
only.
**************************************************************************
a.
Provide a calibration schedule including the anticipated dates when
equipment requiring coordination and protection will be installed, the
anticipated date when the Contractor will submit a formal request for
settings, and the anticipated date when the manufacturer's technical
representative will perform settings and calibrate equipment.
b.
Submit the calibration schedule, via the Contracting Officer to:
SOUTHNAVFACENGCOM, Code 05, Construction Department
SOUTHNAVFACENGCOM; Code 162; Director, Utilities Engineering Division
][1.4.6
Formal Request for Settings
**************************************************************************
NOTE: The "30" days in brackets below may be
extended for projects involving major electrical
distribution work. Consult with SOUTHNAVFACENGCOM
Code 162.
**************************************************************************
a.
Where settings will be provided by the Government to achieve protection
and coordination via relays and protective devices, submit a formal
request for settings [30][____] days in advance of the date that
settings will be needed, to allow the Contracting Officer to forward a
copy of approved shop drawings to SOUTHNAVFACENGCOM; Code 162;
Director, Utilities Engineering Division.
b.
The equipment requiring protection and coordination shall be installed
prior to making this request.
c.
Include approved shop drawings, manufacturer's instructions to set the
d.
Submit the formal request for settings, via the Contracting Officer to:
SOUTHNAVFACENGCOM; Code 162; Director, Utilities Engineering Division.
SECTION 16361N