For Air Handler:
[_____]
Checklist Item
Q
M
E
T
C
D
O
U
Installation
a.
Ductwork complete.
___ ___
X
___
X
___ ___ ___
b.
As-built shop drawings submitted.
___ ___
X
___
X
___ ___ ___
c.
Ductwork leak test complete.
___ ___
X
___
X
___ ___ ___
NOTE: The first bracketed item d will be used for Army projects, the
second for Air Force projects.
[d. Fire dampers, smoke dampers, and
access doors installed as required.
___ ___
X
___
X
___ ___ ___]
[d. Fire dampers, smoke dampers, and
access doors installed as required with
installation of each verified by the
specified team members initialing each
location on a copy of the as-built
drawings.
___ ___
X
___
X
___ ___ ___]
e.
Ductwork insulated as required.
___ ___
X
___
X
___ ___ ___
f.
Thermometers and gauges installed as
required.
___ ___ ___ ___ ___ ___ ___ ___
g.
Verify open/closed status of dampers.
___ ___
X
___
X
___ ___ ___
h.
Verify smoke and fire damper operation.
___ ___
X
___ ___ ___ ___ ___
i.
Flexible connectors installed as specified__ ___
X
___
X
___ ___ ___
Testing, Adjusting, and Balancing (TAB)
a.
TAB operation complete.
___ ___
X
___
X
___ ___ ___
SECTION 15995A