checks.
SD-06 Test Reports
Test Reports[; G][; G, [_____]]
Completed pre-commissioning checklists and functional
performance test checklists organized by system and by subsystem
and submitted as one package. The results of failed tests shall
be included along with a description of the corrective action
taken.
1.2
SEQUENCING AND SCHEDULING
**************************************************************************
NOTE: Provide seismic requirements, if a Government
designer (either Corps office of A/E) is the
Engineer of Record, and show on the drawings.
Delete the bracketed phrase if seismic details are
not included. Sections 13080 and 15070, properly
edited, must be included in the contract documents.
**************************************************************************
The work described in this Section shall begin only after all work required
in related Sections, including Section 15951 DIRECT DIGITAL CONTROL FOR
HVAC AND OTHER LOCAL BUILDING SYSTEMS and Section 15990A TESTING,
ADJUSTING, AND BALANCING OF HVAC SYSTEMS, has been successfully completed,
required in these Sections have been submitted and approved. Seismic
details shall be in accordance with Sections 13080 SEISMIC PROTECTION FOR
MISCELLANEOUS EQUIPMENT and 15070A SEISMIC PROTECTION FOR MECHANICAL
EQUIPMENT [as indicated]
PART 2
PRODUCTS
(Not Applicable)
PART 3
EXECUTION
3.1
COMMISSIONING TEAM AND CHECKLISTS
**************************************************************************
NOTE: The "Design Agent's Representative" will be
participate in the functional performance tests.
The checklists provided are to be used as guides for
the preparation of project checklists. The
appropriate checklist should be included in the
project specification for each HVAC equipment
component. The designer will add additional
checklists for equipment or systems not included in
this guide specification or modify the checklists
where necessary for specific project requirements.
If, for example, a system needs to be tested with
certain internal load, each appropriate checklist
should be modified to include this requirement along
with specifics on how load should be generated.
**************************************************************************