The Contractor shall designate team members to participate in the
herein. In addition, the Government will be represented by a
representative of the Contracting Officer, the Design Agent's
Representative, and the Using Agency. The team members shall be as follows:
Designation
Function
Q
Contractor's
Chief Quality Control Representative
M
Contractor's
Mechanical Representative
E
Contractor's
Electrical Representative
T
Contractor's
Testing, Adjusting, and Balancing
Representative
C
Contractor's Controls Representative
D
Design Agent's Representative
O
Contracting Officer's Representative
U
Using Agency's Representative
Appendices A and B are provided as a general checklist and have been
prepared to best match the various equipment selected during the design of
this project. Each checklist shown in Appendices A and B shall be reviewed
and modified as necessary to reflect equipment actually installed during
construction of the project. The commissioning team shall review the
accuracy and applicability of each item in the checklist and revise as
needed. Equipment shown in the checklist but not installed for the project
shall be annotated as "NA". Likewise, equipment installed but not listed
in the checklist shall be added or revised accordingly. A note as to why
it was added or revised shall be inserted with the reviewer's initial. The
commissioning team shall also add or modify to any of the equipment
checklist items as required and/or specified by the equipment manufacturer.
Acceptance by each commissioning team member of each pre-commissioning
checklist item shall be indicated by initials and date, unless an "X" is
shown indicating that participation by that individual is not required.
Acceptance by each commissioning team member of each functional performance
test checklist shall be indicated by signature and date.
3.2
TESTS
The pre-commissioning checks and functional performance tests shall be
performed in a manner which essentially duplicates the checking, testing,
and inspection methods established in the related Sections. Where
checking, testing, and inspection methods are not specified in other
Sections, methods shall be established which will provide the information
required. Testing and verification required by this section shall be
performed during the Commissioning phase. Requirements in related Sections
are independent from the requirements of this Section and shall not be used
to satisfy any of the requirements specified in this Section. The
Contractor shall provide all materials, services, and labor required to
perform the pre-commissioning checks and functional performance tests. A
pre-commissioning check or functional performance test shall be aborted if
any system deficiency prevents the successful completion of the test or if
any participating non-Government commissioning team member of which
participation is specified is not present for the test. The Contractor
shall reimburse the Government for all costs associated with effort lost
due to tests that are aborted. These costs shall include salary, travel
costs and per diem (where applicable) for Government commissioning team
members. The Contractor shall submit Test Reports as specified in the
Submittals paragraph.