For Air Handling Unit:
[_____]
Checklist Item
Q
M
E
T
C
D
O
U
[d. Steam and condensate piping pressure
tested.
___ ___
X
X
X
___ ___ ___]
e.
Air vents installed on water coils [with
shutoff valves] as specified.
___ ___
X
X
X
___ ___ ___
f.
Any damage to coil fins has been repaired__ ___
X
___
X
___ ___ ___
Controls
a.
Control valves/actuators properly
installed.
___ ___
X
___ ___ ___ ___ ___
b.
Control valves/actuators operable.
___ ___
X
___ ___ ___ ___ ___
c.
O.A. dampers/actuators properly installed.__ ___
X
___ ___ ___ ___ ___
d.
O.A. dampers/actuators operable.
___ ___
X
___ ___ ___ ___ ___
e.
Zone dampers/actuators properly installed.__ ___
X
___ ___ ___ ___ ___
f.
Zone dampers/actuators operable.
___ ___
X
___ ___ ___ ___ ___
Testing, Adjusting, and Balancing (TAB)
a.
Construction filters removed and replaced.__ ___
X
___
X
___ ___ ___
b.
TAB report submitted.
___ ___
X
___
X
___ ___ ___
c.
TAB results within limits specified
in Section 15990A
d.
TAB results for outside air intake within
limits specified in Section 15990A
___ ___
X
___
X
___ ___ ___
SECTION 15995A
Page 10