3.2.1
Pre-Commissioning Checks
Pre-commissioning checks shall be performed for the items indicated on the
checklists in Appendix A. Deficiencies discovered during these checks
shall be corrected and retested in accordance with the applicable contract
requirements.
3.2.2
Functional Performance Tests
Functional performance tests shall be performed for the items indicated on
the checklists in Appendix B. Functional performance tests shall begin
only after all pre-commissioning checks have been successfully completed.
Tests shall prove all modes of the sequences of operation, and shall verify
all other relevant contract requirements. Tests shall begin with equipment
or components and shall progress through subsystems to complete systems.
Upon failure of any functional performance test checklist item, the
Contractor shall correct all deficiencies in accordance with the applicable
contract requirements. The checklist shall then be repeated until it has
been completed with no errors.
SECTION 15995A
Page 6