1.8.3
Responsibilities
The Contractor shall be responsible for ensuring compliance with the
requirements of this section. The following delineation of specific work
responsibilities is specified to facilitate execution of the various work
efforts by personnel from separate organizations. This breakdown of
specific duties is specified to facilitate adherence to the schedule listed
in paragraph entitled "TAB Submittal and Work Schedule."
1.8.3.1
Contractor
a.
TAB personnel: Ensure that [the DALT work and ]the TAB work is
accomplished by a group meeting the requirements specified in
paragraph entitled "TAB Personnel Qualification Requirements."
b.
Pre-[DALT/]TAB meeting: Attend the meeting with the TAB
Supervisor, and ensure that a representative is present for the
sheetmetal contractor, mechanical contractor, electrical
contractor, and automatic temperature controls contractor.
c.
HVAC documentation: Furnish one complete set of the following
HVAC-related documentation to the TAB agency:
(1)
Contract drawings and specifications
(2)
Approved submittal data for equipment
(3)
Construction work schedule
(4) Up-to-date revisions and change orders for the previously
listed items
d.
Submittal and work schedules: Ensure that the schedule for
submittals and work required by this section and specified in
paragraph entitled "TAB Submittal and Work Schedule," is met.
e.
Coordination of supporting personnel:
Provide the technical personnel, such as factory representatives
or HVAC controls installer required by the TAB field team to
support [the DALT and ]the TAB field measurement work.
Provide equipment mechanics to operate HVAC equipment and ductwork
mechanics to provide the field designated test ports to enable TAB
field team to accomplish [the DALT and ]the TAB field measurement
work. Ensure these support personnel are present at the times
required by the TAB team, and cause no delay in [the DALT and]the
TAB field work.
Conversely, ensure that the HVAC controls installer has required
support from the TAB team field leader to complete the controls
check out.
f.
Deficiencies: Ensure that the TAB Agency supervisor submits all
Design/Construction deficiency notifications directly to the
Contracting officer within 3 days after the deficiency is
encountered. Further, the Contractor shall ensure that all such
notification submittals are complete with explanation, including
documentation, detailing deficiencies.