NOTE: The number of workdays for the TAB
supervisor's visits to the contract work site for
TAB work, shall be based on the size, number, type,
and complexity of the HVAC system to be TAB'd.
**************************************************************************
**************************************************************************
NOTE: Choose one of the following options.
**************************************************************************
**************************************************************************
NOTE: Option 1: Normally, use the following two
subparagraphs, which requires two separate trips
within a season to the contract site by the TAB
field team (the first for the TAB field work, the
certified TAB report submitted between the trips.
This is intended to give the design engineer time to
review the certified TAB report before the field
check of that report is conducted.
**************************************************************************
[(1) TAB field visit: At the midpoint of the Season 1 and Season
2 TAB field work effort, visit the contract site to inspect the
HVAC installation and the progress of the TAB field work. Conduct
site visit full-time for a minimum of [one] [two] [_____] 8 hour
workday[s] duration.]
[(2) TAB field visit: Near the end of the TAB field work effort,
visit the contract site to inspect the HVAC installation and the
progress of the TAB field work. Conduct site visit full-time for
a minimum of [one] [two] [_____] 8 hour workday[s] duration.
Review the TAB final report data and certify the TAB final report.]
**************************************************************************
NOTE: Option 2: Use the following subparagraph
when the contract site is remote, or the HVAC system
is simple, and the specifier wants to reduce to one
the number of trips to the contract site by the TAB
field team within a season (TAB field work and TAB
**************************************************************************
[(1) TAB field visit: Near the end of the TAB field work effort,
visit the contract site to inspect the HVAC installation and the
progress of the TAB field work. Conduct site visit full-time for
a minimum of [one] [two] [_____] 8 hour workday[s] duration.
Review the TAB final report data and certify the TAB final report.]
k.
Certified TAB report: Certify the TAB report.
This certification
includes the following work:
(1) Review: Review the TAB field data report.
From this field
report, prepare the certified TAB report.
(2) Verification: Verify adherence, by the TAB field team, to
the TAB plan prescribed by the pre-field engineering report and