[1.8.2.3
Pre-Field DALT Preliminary Notification
a.
Notification: On completion of the installation of each duct
system indicated to be DALT'd, the Contractor shall notify the
Contracting Officer in writing within 7 calendar days after
completion.]
1.8.2.4
Pre-Field TAB Engineering Report
Submit report containing the following information:
a.
Step-by-step TAB procedure:
(1) Strategy: Describe the method of approach to the TAB field
work from start to finish. Include in this description a complete
methodology for accomplishing each seasonal TAB field work session.
(2) Procedural steps: Delineate fully the intended procedural
steps to be taken by the TAB field team to accomplish the required
TAB work of each air distribution system and each water
distribution system. Include intended procedural steps for TAB
work for subsystems and system components.
b.
Pre-field data: Submit AABC or NEBB or SMACNA HVACTAB data report
forms with the following pre-field information filled in:
(1) Design data obtained from system drawings, specifications,
and approved submittals.
(2) Notations detailing additional data to be obtained from the
contract site by the TAB field team.
(3) Designate the actual data to be measured in the TAB field
work.
(4) Provide a list of the types of instruments, and the measuring
range of each, which are anticipated to be used for measuring in
the TAB field work. By means of a keying scheme, specify on each
TAB data report form submitted, which instruments will be used for
measuring each item of TAB data. If the selection of which
instrument to use, is to be made in the field, specify from which
instruments the choice will be made. The instrument key number
shall be placed in the blank space where the measured data would
be entered.
c.
Prerequisite HVAC work checkout list: Provide a list of
inspections and work items which are to be completed by the
Contractor. This list shall be acted upon and completed by the
Contractor and then submitted and approved by the Contracting
Officer prior to the TAB team coming to the contract site.
At a minimum, a list of the applicable inspections and work items
listed in the NEBB TABES, Section III, "Preliminary TAB
Procedures" under paragraphs titled, "Air Distribution System
Inspection" and "Hydronic Distribution System Inspection" shall be
provided for each separate system to be TAB'd.