TAB report submitted between trips. This is
intended to give the design engineer time to review
the certified TAB report before the field check of
that report is conducted.
**************************************************************************
[Season 2 TAB Field Work: Within [180] [_____] calendar days
after date of commencement of the Season 1 TAB field work and when
the ambient temperature is within Season 2 limits, accomplish
Season 2 TAB field work.
Submit Season 2 TAB Report: Within [15] [_____] calendar days
after completion of Season 2 TAB field work, submit certified
Season 2 TAB report.
Season 2 TAB Field Check: [30] [_____] calendar days after the
certified Season 2 TAB report is approved by the Contracting
Officer, conduct Season 2 field check.
Complete Season 2 TAB Work: Within [15] [_____] calendar days
after the completion of Season 2 TAB field data check, complete
all TAB work.]
**************************************************************************
NOTE: Option 2: Use the following two paragraphs
when the contract site is remote, or the HVAC system
is simple, and the specifier wants to reduce to one
the number of trips to the contract site by the TAB
field team within Season 2 (TAB field work and TAB
Renumber remaining paragraphs appropriately.
**************************************************************************
[Season 2 TAB Field Work:
Within
[180] [_____] calendar days
after date of commencement
of the
Season 1 TAB field work and when
the ambient temperature is
within
Season 2 limits, accomplish
[Season 2] TAB field work;
submit
[Season 2] certified TAB report;
and conduct Season 2 field
check.
Complete Season 2 TAB Work: Within [15] [_____] calendar days
after the completion of Season 2 field data check, complete TAB
work.]
1.8
QUALITY ASSURANCE
1.8.1
Modifications of References
Accomplish work in accordance with referenced publications of AABC or NEBB
except as modified by this section. In the references referred to herein,
consider the advisory or recommended provisions to be mandatory, as though
the word "shall" had been substituted for the words "should" or "could" or
"may" wherever they appear. Interpret reference to the "authority having
jurisdiction," the "Administrative Authority," the "Owner," or the "Design
Engineer" to mean the "Contracting Officer."
SECTION 15950N