installed test ports and other devices needed, including gauge
cocks, thermometer wells, flow control devices, circuit setters,
balancing valves, and manual volume dampers.
d.
Support required: Specify the technical support personnel
required from the Contractor other than the TAB agency; such as
factory representatives for temperature controls or for complex
equipment. Inform the Contractor in writing of the support
personnel needed and when they are needed. Furnish the notice as
soon as the need is anticipated, either with the design review
report, or the pre-field engineering report, the during the [DALT
or ]TAB field work.
[e.
Pre-field DALT preliminary notification: Monitor the completion
of the duct installation of each system and provide the necessary
written notification to the Contracting Officer.]
f.
Pre-field engineering report: Utilizing the following
HVAC-related documentation; contract drawings and specifications,
approved submittal data for equipment, up-to-date revisions and
change orders; prepare this report.
g.
Prerequisite HVAC work checklist: Ensure the Contractor gets a
copy of this checklist at the same time as the pre-field
engineering report is submitted.
[h.
Technical assistance for DALT work.
(1) Technical assistance:
Provide immediate technical assistance
to TAB field team.
**************************************************************************
NOTE: The number of workdays for the TAB
supervisor's visit to the contract site for DALT
work, shall be based on the size, number, type, and
complexity of the HVAC system to be DALT'd.
**************************************************************************
(2) DALT field visit: Near the end of the DALT field work effort,
visit the contract site to inspect the HVAC installation and the
progress of the DALT field work. Conduct a site visit to the
extent necessary to verify correct procedures are being
implemented and to confirm the accuracy of the Pre-final DALT
Report data which has been reported. Also, sufficient evaluation
shall be made to allow the TAB supervisor to issue certification
of the final report. Conduct the site visit full-time for a
minimum of [one] [two] [_____] 8 hour workday[s] duration.]
[i.
Certified Final DALT report: Certify the DALT report.
This
certification includes the following work:
(1) Review: Review the Pre-final DALT report data. From these
field reports, prepare the Certified Final DALT report.
(2) Verification: Verify adherence, by the TAB field team, to
the procedures specified in this section.]
j.
Technical Assistance for TAB Work: Provide immediate technical
assistance to the TAB field team for the TAB work.