c.
Certification: Include the typed name of the TAB supervisor and
the dated signature of the TAB supervisor.
]1.8.4.2
Certified TAB Reports
Submit Certified TAB Report for Season 1 and Certified TAB Report for
Season 2 in the following manner:
a.
Report format: Submit the completed pre-field data forms approved
in the pre-field TAB Engineering Report completed by TAB field
team, reviewed and certified by the TAB supervisor. Bind the
report with a waterproof front and back cover. Include a table of
contents identifying by page number the location of each report.
Report forms and report data shall be typewritten. Handwritten
report forms or report data are not acceptable.
b.
Temperatures: On each TAB report form reporting TAB work
accomplished on HVAC thermal energy transfer equipment, include
the indoor and outdoor dry bulb temperature range and indoor and
outdoor wet bulb temperature range within which the TAB data was
recorded. Include in the TAB report continuous time versus
temperature recording data of wet and dry bulb temperatures for
the rooms, or zones, as designated in the following list:
**************************************************************************
NOTE: The design engineer shall list, in the
paragraph below, those rooms, or zones, for which
indoor dry bulb and wet bulb temperatures shall be
compiled for the specified time duration. Include a
sufficient number of rooms, or zones, in the listing
to ensure correct evaluation of performance for the
installed HVAC systems.
**************************************************************************
(1) [Specifier: List desired rooms and/or zones here]. Data
shall be measured and compiled on a continuous basis for the
period in which TAB work affecting those rooms is being done.
(2) Data shall be measured/recorded only after the HVAC systems
installations are complete, the systems fully balanced and the
HVAC systems controls operating in fully automatic mode.
(3) Data may be compiled using direct digital controls trend
logging where available. Otherwise, the Contractor shall
temporarily install calibrated time versus temperature/humidity
recorders for this purpose. The HVAC systems and controls shall
have been fully operational a minimum of 24 hours in advance of
commencing data compilation. The specified data shall be included
in the [Season I TAB Report] [Season I and Season 2 TAB Report].
**************************************************************************
NOTE: Paragraphs c., d., and e., below apply to air
distribution systems to be TAB'd. Delete all of
these paragraphs if no air distribution systems are
in the project, or delete the paragraphs not
applicable and edit the terminology of the remaining
paragraphs to agree with the drawings.
**************************************************************************
SECTION 15950N
Page 20