upgrades or downgrades (whichever is appropriate based on exposure) on
the use of PPE (respirators included) and engineering controls.
e. Ensure work is performed in strict accordance with specifications at
all times.
f. Control work to prevent hazardous exposure to human beings and to
the environment at all times.
g. Supervise final cleaning of the lead control area, take clearance
wipe samples if necessary; review clearance sample results and make
recommendations for further cleaning.
h. Certify the conditions of the work as called for elsewhere in this
specification.
1.5.2.2
Lead Compliance Plan
**************************************************************************
NOTE: State or local regulations may have specific
requirements for written project designs. Research
specific State or local requirements for public,
commercial buildings or structures.
Consider the
bracketed occupant protection plan for high profile
sensitive work such as present in family housing,
childcare facilities, administrative buildings,
kitchens, etc.
**************************************************************************
Submit a detailed job-specific plan of the work procedures to be used in
the disturbance of PWL or MCL. The plan shall include a sketch showing the
location, size, and details of lead control areas, critical barriers,
physical boundaries, location and details of decontamination facilities,
viewing ports, and mechanical ventilation system. Include a description of
equipment and materials, work practices, controls and job responsibilities
for each activity from which lead is emitted. Include in the plan, eating,
drinking, smoking, hygiene facilities and sanitary procedures, interface of
trades, sequencing of lead related work, collected waste water and dust
containing lead and debris, air sampling, respirators, personal protective
equipment, and a detailed description of the method of containment of the
operation to ensure that lead is not released outside of the lead control
occupational and environmental sampling, training and strategy, sampling
and analysis strategy and methodology, frequency of sampling, duration of
sampling, and qualifications of sampling personnel in the air sampling
portion of the plan. Include a description of arrangements made among
contractors on multicontractor worksites to inform affected employees and
to clarify responsibilities to control exposures.
[ The plan shall be developed by a certified planner/project designer in the
State of [_____].]
[ In occupied buildings, the plan shall also include an occupant protection
program that describes the measures that will be taken during the work to
[notify and] protect the building occupants.]
1.5.2.3
Occupational and Environmental Assessment Data Report
**************************************************************************
SECTION 13282N
Page 11