Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
**************************************************************************
NOTE: The submittals required for each project are
very dependent upon the removal method to be used.
Edit the submittals paragraph accordingly.
**************************************************************************
SD-03 Product Data
Vacuums; G
Respirators; G
Pressure differential automatic recording instrument; G
Amended water; G
[
Glovebags; G]
transport to the project site; G
Encapsulants; G
SD-06 Test Reports
Air sampling results; G
Pressure differential recordings for local exhaust system; G
Asbestos disposal quantity report; G
Encapsulation test patches; G
Clearance sampling; G
SD-07 Certificates
**************************************************************************
NOTE: Include contractor's and worker's licenses
for Virginia projects.
**************************************************************************
Asbestos hazard abatement plan; G
Testing laboratory; G
Private qualified person documentation; G
[
Contractor's license; G]
SECTION 13281N
Page 17