requirements of ASTM C 171.
Nonshrink Grout[; G][; G, [_____]]
Descriptive literature of the grout proposed for use containing
certified laboratory test results showing that it meets ASTM C 1107
shall be submitted 60 days prior to its use together with a
certificate from the manufacturer stating that the grout is
suitable for the application or exposure for which it is being
considered. In addition, a detailed plan shall be submitted for
review, showing equipment and procedures for use in mixing and
placing the grout.
Descriptive literature and certification in advance of their use.
Expansive Admixture
Manufacturer's descriptive literature and certification for
fluidifier to be used as expansive admixture in block-out
concrete, 60 days prior to its use.
1.6
MATERIAL DELIVERY, STORAGE, AND HANDLING
1.6.1
Cementitious Materials
1.6.1.1
Transportation
When bulk cement, pozzolan, dry silica fume, or ground granulated
blast-furnace slag is not unloaded from primary carriers directly into
weather-tight hoppers at the batching plant, transportation from the
railhead, mill, or intermediate storage to the batching plant shall be
accomplished in adequately designed weather-tight trucks, conveyors, or
other means that will protect the material from exposure to moisture.
Transportation facilities for dry bulk silica fume shall be approved in
advance.
1.6.1.2
Storage
Cementitious materials shall be furnished in bulk except that cement used
for finishing and patching may be packaged, and silica fume may be packaged
or in slurry form. Immediately upon receipt at the site of the work, all
cementitious materials, shall be stored in separate dry, weather-tight, and
properly ventilated structures. All storage facilities shall permit easy
access for inspection and identification. Sufficient materials shall be in
storage to complete any lift of concrete started. In order that cement may
not become unduly aged after delivery, the Contractor shall use any cement
that has been stored at the site for 60 days or more before using cement of
lesser age. Silica fume in slurry form that has been in storage at the
project site for longer than recommended by the manufacturer or that has
been subjected to freezing shall not be used in the work and shall be
removed from the site.
1.6.1.3
Separation of Materials
Separate facilities shall be provided for unloading, transporting, and
handling each cementitious material. Separate appropriate storage
facilities shall be provided for each type of cement and each source of
SECTION 03700
Page 34