for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Concrete Lifts[; G][; G, [_____]]
A lift drawing and bill of materials shall be furnished for each
lift of concrete. (Only one lift shall be shown on a drawing).
These drawings shall be to scale and shall show all embedded items
in sufficient detail for the proper installation and prosecution
of the work. All embedded electrical and/or mechanical items
shall be identified. The drawings shall not be less than 594 by
841 mm 22 by 34 inches in size and the scale used shall be
sufficiently large to clearly show all details of the structure
covered by these drawings. A note shall be included on each lift
drawing indicating all contract drawings from which the lift
drawing was prepared. The Contractor shall submit [_____] copies
of each drawing for review at least 60 days prior to scheduling
the lift for placement.
Equipment[; G][; G, [_____]]