The methods and description of the equipment proposed for
transporting, handling, and depositing the concrete shall be
submitted for review 60 days before concrete placement begins.
The data submitted shall include site drawings or sketches with
locations of equipment and placement site.
SD-03 Product Data
Batch Plant[; G][; G, [_____]]
Details and data on the concrete plant shall be submitted within
60 days prior to assembly to the Contracting Officer for
conformance review with the requirements of paragraph EQUIPMENT.
Mixers
The make, type, capacity, and number of the concrete mixers
proposed for use shall be submitted 60 days prior to installation
for review by the Contracting Officer for conformance with the
requirements of paragraph EQUIPMENT.
Construction Joint Treatment[; G][; G, [_____]]
The method and equipment proposed for joint cleanup and waste
disposal shall be submitted for review 30 days before concrete
placement begins.
Curing and Protection[; G][; G, [_____]]
The curing media and methods to be used shall be submitted for
review 30 days before concrete placement begins.
When concrete is to be placed under cold-weather conditions, a
description of the materials and methods proposed for protection
of the concrete shall be furnished 60 days in advance of
anticipated need date for review.
Hot-Weather Placing[; G][; G, [_____]]
When concrete is to be placed under hot-weather conditions, a
description of the materials and methods proposed for protection
of the concrete shall be furnished 60 days in advance of
anticipated need date for review.
Special Temperature-Controlled Concrete[; G][; G, [_____]]
When special temperature controls are required, all methods and
equipment shall be submitted for review and comment 60 days in
advance of anticipated date required for use.
SD-07 Certificates
Sheet Curing
If sheet curing is used, a manufacturer's certificate shall be
furnished certifying that the materials complies with the