projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-03 Product Data
Piles; G, [_____]
Pile driving equipment; G, [_____]
Submit complete descriptions of pile driving equipment,
including hammers, leads, driving helmets, cushion blocks, driving
blocks, collars, extractors, and other appurtenances for approval
prior to commencement of work.
[
Pile caps; G, [_____]]
[
Pile shoes; G, [_____]]
[
Jetting equipment; G, [_____]]
[
Spudding equipment; G, [_____]]
[
Predrilling equipment; G, [_____]]
[
Spliced piles; G, [_____]]
[
The splice design for piles shall be submitted for approval
prior to use in the work.]
[
SD-04 Samples
Test piles; G, [_____]
If approved after test completion, include properly located test
piles in finished work.]
SD-06 Test Reports
[
Load tests; G, [_____]
Test data and results as specified in paragraph entitled "Load
Tests."]
A certified test assay analysis from an approved testing
organization attesting that the piles to be used in the work have
specifications shall be submitted prior to commencement of the
work.
SECTION 02461
Page 7