INCREASE IN LENGTH
FACTOR
(OVER [_____] METERS)
(INCLUSIVE)
0.1
to
1.5
meters
.......................
1.05
1.6
to
3.0
meters
.......................
1.10
3.1
to
4.5
meters
.......................
1.15
4.6
to
6.0
meters
.......................
1.30
6.1
to
7.5
meters
.......................
1.50
INCREASE IN LENGTH
FACTOR
(OVER [_____] FEET)
(INCLUSIVE)
0.1
to
5.0
feet
.......................
1.05
5.5
to
10.0
feet
.......................
1.10
10.5
to
15.0
feet
.......................
1.15
15.5
to
20.0
feet
.......................
1.30
20.5
to
25.0
feet
.......................
1.50
1.6.1.2
Measurement
Acceptably driven piles will be measured for payment based upon the lengths
in place below the cutoff elevation. The cutoff portion of any pile,
except the 300 millimeters 1 foot provided for heading, will be measured
for payment as the length of such cutoff portion which does not exceed the
difference between the length of pile specified to be driven below the
cutoff elevation and the length actually driven below the grade. Pile and
cutoff length will be measured to the nearest 100 millimeters 1/2 foot.
1.6.1.3
Unit of Measure
Unit of measure:
linear meter foot.
[1.6.2
Test Piles
]1.6.2.1
Payment
Payment will be made for test piles, driven as directed and not
incorporated in the permanent work. Payment will be made for test piles
incorporated in the permanent work.
1.6.2.2
Measurement
Test piles, driven as directed and not incorporated in the permanent work,
will be measured for payment at twice the applicable contract unit price
for a permanent pile of the same type and length, except that the specified
length of test pile will be considered to have been driven below cutoff
elevation whether or not so driven. Test piles, incorporated in the
permanent work, will be measured for payment at the contract price per
linear meter foot for permanent piles.
1.6.2.3
Unit of Measure
Unit of measure:
linear meter foot.
[1.6.3
Pile Load Tests
**************************************************************************
NOTE: The designer will specify the number of pile
SECTION 02461
Page 12