a.
CCTV system equipment items and DTM have been set up in accordance
with manufacturer's instructions.
b.
A visual inspection of the CCTV system has been conducted to
ensure that defective equipment items have not been installed and
that there are no loose connections.
c.
System wiring has been tested and verified as correctly connected
as indicated.
d.
All system grounding and transient protection systems have been
verified as properly installed and connected as indicated.
e.
verified as the correct voltage, phasing, and frequency as
indicated.
f.
Satisfaction of the above requirements shall not relieve the
Contractor of responsibility for incorrect installation, defective
equipment items, or collateral damage as a result of Contractor
work/equipment.
3.3
SUPPLEMENTAL CONTRACTOR QUALITY CONTROL
**************************************************************************
NOTE: The contractor quality control requirements
for all IDS projects, as stated in ER 1180-1-6,
shall be included in contracts, regardless of
increase in project cost. Normally this contractor
quality control requirement is applicable to
projects in excess of
||content||
,000,000.
**************************************************************************
The following requirements supplement the contractor quality control
requirements specified elsewhere in the contract. The contractor shall
provide the services of technical representatives who are thoroughly
familiar with all components and installation procedures of the installed
IDS; and are approved by the Contracting Officer. These representatives
will be present on the job site during the preparatory and initial phases
of quality control to provide technical assistance. These representatives
shall also be available on an as needed basis to provide assistance with
follow-up phases of quality control. These technical representatives shall
participate in the testing and validation of the system and shall provide
certification that their respective system portions meet its contractual
requirements.
3.4
SITE TESTING
3.4.1
General
The Contractor shall provide all personnel, equipment, instrumentation, and
supplies necessary to perform all site testing. The Government will
witness all performance verification and endurance testing. Written
permission shall be obtained from the Government before proceeding with the
next phase of testing. Original copies of all data produced during
performance verification and endurance testing shall be turned over to the
Government at the conclusion of each phase of testing prior to Government
approval of the test.