b.
Three video monitors.
c.
Video recorder if it is required for the installed system.
d.
Video switcher including video input modules, video output
modules, and control and applications software.
e.
Video multiplexer, if required for the installed system.
f.
Alarm input panel if required for the installed system.
g.
Pan/tilt mount and pan/tilt controller if the installed system
includes cameras on pan/tilt mounts.
h.
Any ancillary equipment associated with a camera circuit such as
equalizing amplifiers, video loss/presence detectors, terminators,
ground loop correctors, surge protectors or other in-line video
devices.
i.
Cabling for all components.
PART 3
EXECUTION
3.1
INSTALLATION
**************************************************************************
NOTE: Electric metallic tubing (EMT) may be
considered for use if it is used solely within the
secure protected area.
**************************************************************************
The Contractor shall install all system components including Government
furnished equipment, and appurtenances in accordance with the
manufacturer's instructions, IEEE C2 and as shown, and shall furnish all
adjustments required for a complete and operable system. Raceways shall be
furnished and installed as specified in Section 16375A ELECTRICAL
DISTRIBUTION SYSTEM, UNDERGROUND and Section 16402 INTERIOR DISTRIBUTION
SYSTEM. DTM shall not be pulled into conduits or placed in raceways,
compartments, outlet boxes, junction boxes, or similar fittings with other
building wiring. All other electrical work shall be as specified in the
above sections including grounding to preclude ground loops, noise, and
surges from adversely affecting system operation.
3.1.1
Current Site Conditions
The Contractor shall visit the site and verify that site conditions are in
agreement with the design package. The Contractor shall report all changes
to the site or conditions that will affect performance of the system to the
Government in a report as defined in paragraph Group II Technical Data
Package. The Contractor shall not take any corrective action without
written permission from the Government.
3.1.2
Existing Equipment
The Contractor shall connect to and utilize existing video equipment, video
equipment and signal lines that are usable in their original configuration
without modification may be reused with Government approval. The
SECTION 16751A