verification that the control performs the designed function.
g.
Verification that all video sources and video outputs provide a
full bandwidth signal that complies with EIA 170 at all video
inputs.
h.
Verification that all video signals are terminated properly.
i.
Verification that all cameras are aimed and focused properly. The
Contractor shall conduct a walk test of the area covered by each
camera to verify the field of view.
j.
Verification that cameras facing the direction of rising or
setting sun are aimed sufficiently below the horizon so that the
camera does not view the sun directly.
k.
If vehicles are used in proximity of the assessment areas,
verification of night assessment capabilities and determination if
headlights cause blooming or picture degradation.
l.
Verification that all cameras are synchronized and that the
picture does not roll when cameras are switched.
m.
Verification that the alarm interface to the IDS is functional and
that automatic camera call-up is functional with appropriate video
annotation for all designated ESS alarm points and cameras.
n.
When pan/tilt mounts are used in the system, verification that the
limit stops have been set correctly. Verification of all controls
for pan/tilt or zoom mechanisms are operative and that the
controls perform the desired function. If preposition controls
are used, verification that all home positions have been set
correctly, and have been tested for auto home function and correct
home position.
o.
When dome camera mounts are used in the system, verify that all
preset positions are correct and that the dome also operates
correctly in a manual control mode.
The Contractor shall deliver a report describing results of functional
tests, diagnostics, and calibrations including written certification to the
Government that the installed complete system has been calibrated, tested,
and is ready to begin performance verification testing. The report shall
also include a copy of the approved performance verification test procedure.
3.4.3
Performance Verification Test
The Contractor shall demonstrate that the completed CCTV system complies
with the contract requirements. Using approved test procedures, all
physical and functional requirements of the project shall be demonstrated
and shown. The performance verification test, as specified, shall not be
started until receipt by the Contractor of written permission from the
Government, based on the Contractor's written report. This shall include
certification of successful completion of Contractor Field Testing as
specified in paragraph "Contractor's Field Testing," and upon successful
completion of training as specified. If the CCTV system is being installed
in conjunction with an ESS, the CCTV performance verification test shall be
run simultaneously with the ESS performance verification test. The
Government may terminate testing at any time when the system fails to
SECTION 16751A
Page 43