e.
Switcher operating and maintenance instructions.
f.
Manuals for CCTV equipment.
g.
Data entry forms.
1.3.1.4
Software Data
The data package shall consist of descriptions of the operation and
capability of system and application software as specified.
1.3.1.5
The data package shall include all manufacturer's reliability data and
calculations required to show compliance with the specified reliability.
The calculations shall be based on all CCTV equipment associated with one
camera circuit and the console CCTV equipment, excluding the data
transmission media (DTM).
1.3.1.6
Certifications
All specified manufacturer's certifications shall be included with the data
package.
1.3.1.7
Key Control Plan
**************************************************************************
The Contractor shall provide a key control plan as
specified in Section 13720A ELECTRONIC SECURITY
SYSTEM.
**************************************************************************
The Contractor shall provide a key control plan as specified in Section
13720A ELECTRONIC SECURITY SYSTEM.
1.3.2
Group II Technical Data Package
The Contractor shall verify that site conditions are in agreement with the
design package. The Contractor shall submit a report to the Government
documenting changes to the site, or conditions that affect performance of
the system to be installed. For those changes or conditions which affect
system installation or performance, provide (with the report) specification
sheets, or written functional requirements to support the findings, and a
cost estimate to correct the deficiency. The Contractor shall not correct
any deficiency without written permission from the Government.
1.3.3
Group III Technical Data Package
The Contractor shall prepare test procedures and reports for the
predelivery test. The Contractor shall deliver the predelivery test
procedures to the Government for approval. After receipt by the Contractor
of written approval of the predelivery test procedures, the Contractor may
schedule the predelivery test. The final predelivery test report shall be
delivered after completion of the predelivery test.
SECTION 16751A