c.
The Government will determine the acceptability of any proposed system
Contractor, Installer and Manufacturer based on submitted and verified
documentation that substantiates that the proposed system Contractor,
Installer and Manufacturer have the qualifications specified in this
Section.
d.
The project Electrical Contractor shall not procure or install the
system cabling or equipment unless said Electrical Contractor is separately
and distinctly qualified as the system Contractor and or Installer in
accordance with the qualifications specified in this Section.
e.
The system Contractor shall submit documented verification of the
specified qualifications as part of the Preconstruction qualification
submittal. The Government will have the right to request, inspect and
verify references and resumes of all technical and managerial personnel
assigned to the project. Qualification documentation shall include, but
not be limited to the information outlined below.
**************************************************************************
NOTE: If the NCTV System is to be procured and
provided as part of the facility construction
contract, include the following paragraph "(1)".
If the NCTV System is to be provided as part of a
separate RFP procurement of telecommunications
systems, then delete the following paragraph "(1)".
**************************************************************************
(1 A list of projects performed by the system Contractor and Installer
during the last five years explicitly involving the type of system specified
in this Section. The list shall include the name of the facility where the
work was done, and the name, title, address and telephone number of a point
of contact for the listed facility that can verify the work done. Lists
shall be restricted to the facilities where the type of system delivered and
installed are similar to and serve the same purpose as the system specified
in this Section. Lists shall explicitly identify the make and model of the
systems provided, and the total scope of work done for each and every
facility on the list.
(2) An organization chart for the system Contractor and Installer
project team that will perform the work of this Section.
(3) List and resumes of the principal personnel that will be assigned
to work on this project and their assigned work responsibility and
relationship with the project management structure. This shall include the
following personnel:
System Project Manager
System Application Designer
CAD Staff (that will prepare submittal drawings)
Installation Technical and Supervisory Personnel
Acceptance Testing Personnel
Training Personnel
For each individual, this shall include his or her education and experience
explicitly relevant to their work assignment on this project, and also
include the certificate for factory training where this qualification is
specified. Experiences with other types of systems unrelated to the type of
SECTION 16731A
Page 32