minimum of 5 rings from which material may readily be removed and
replaced, including a separate section for each test. Sections
shall be separated by heavy plastic dividers with tabs.
certifications.
b.
A copy of all measurements taken.
c.
The dates of testing.
d.
The equipment and values verified.
e.
The condition specified for the test.
f.
The test results, signed and dated.
g.
A description of all adjustments made.
h.
Final position of controls, and device settings.
SD-07 Certificates
Material and Equipment
Where materials or equipment are specified to conform to the
standards of the Underwriters Laboratories, Inc., (UL) or to be
constructed or tested, or both, in accordance with the standards
of the American National Standards Institute (ANSI), the Institute
of Electrical and Electronics Engineers (IEEE), or the National
Electrical Manufacturers Association (NEMA), the Contractor shall
submit proof that the items provided under this section of the
specifications conform to such requirements. The label of, or
listing by, UL will be acceptable evidence that the items conform
thereto. Either a certification or a published catalog
specification data statement, to the effect that the item is in
accordance with the referenced ANSI or IEEE standard, will be
acceptable evidence that the item conforms thereto. A similar
certification or published catalog specification data statement to
the effect that the item is in accordance with the referenced NEMA
standard, by a company listed as a member company of NEMA, will be
acceptable evidence that the item conforms thereto. In lieu of
such certification or published data, the Contractor may submit a
certificate from a recognized testing agency equipped and
competent to perform such services, stating that the items have
been tested and that they conform to the requirements listed,
including methods of testing of the specified agencies.
Compliance with above-named requirements does not relieve the
Contractor from compliance with any other requirements of the
specifications.
SD-10 Operation and Maintenance Data
within [7] [_____] calendar days following the completion of tests
and including assembly, installation, operation and maintenance
instructions, spare parts data which provides supplier name,