Material and Equipment
A complete itemized listing of equipment and materials proposed
for incorporation into the work shall be submitted. Each entry
shall include an item number, the quantity of items proposed, and
the name of the manufacturer of each such item.
General Installation Requirements
As a minimum, the Contractor shall submit installation
procedures for station buses and insulators, station structures,
transformers, switchgear, battery system, voltage regulators and
grounding resistors. Procedures shall include diagrams,
instructions, and precautions required to install, adjust,
calibrate, and test the devices and equipment.
Onsite Tests[; G][; G, [_____]]
A detailed description of the Contractor's proposed procedures
for on-site tests.
SD-06 Test Reports
[Six] [_____] copies of the information described below in 215.9
x 279.4 mm (8 1/2 x 11 inch) 8 1/2 x 11 inch binders having a
minimum of 5 rings from which material may readily be removed and
replaced, including a separate section for each test. Sections
shall be separated by heavy plastic dividers with tabs.
certifications.
b.
A copy of all measurements taken.
c.
The dates of testing.
d.
The equipment and values to be verified.
e.
The condition specified for the test.
f.
The test results, signed and dated.
g.
A description of all adjustments made.
Field Testing[; G][; G, [_____]]
A detailed description of the Contractor's proposed procedures
for on-site tests submitted [20] [30] [_____] days prior to
testing the installed system. No field test will be performed
until the test plan is approved. The test plan shall consist of
complete field test procedures including tests to be performed,
test equipment required, and tolerance limits.
Field Test Reports[; G][; G, [_____]]
[Six] [_____] copies of the information described below in 215.9
x 279.4 mm (8 1/2 x 11 inch) 8 1/2 x 11 inch binders having a
SECTION 16311A
Page 15